Hi,
Thanks all for your answer. I understand also that this forum is more technical (some analysis that i read with google translate are pretty impressive), but was trying my chance if someone had similar case. But yes, i will follow now your advices and links.
Thanks for the links (Omakotiliitto /
https://www.kkv.fi/ kuluttajaneuvonta ), very useful, we are checking those in detail with my wife.
I might not have been clear enough but they have already dig the hole, put the pipe and fill it (so the only step left is to put the määlämpo/ Bosh system)
For the latest question, excellent question.
1 company proposed the full package drilling / bosh 70001ghw ) . Target was exactly to avoid those situations and to have everything included)
The contractor was on charge of asking the permission (we have been invoiced for this at least ) and ordered the sub contractor to dig the hole and put the pipes :
From the list of tasks for the Lämpökaivo part in the contract are :
"Lämpökaivo
Lämpökaivo 1 kpl
Yhden lämpökaivon syvyys, 40mm keruuputkistolla 220 m
Alkumetrit teräsputkiporaus 3m per kaivo
Läpiviennit
Pölynsidontakontti
Lämpökaivon teräskansi 1 kpl
Kaivuutyö 11 m
Vaakaputket 11 m
Toimenpideluvan haku 1 kpl"
2 weeks ago, we got a call, "people are coming Monday" that's all. Now we get the info that that was a mistake..

.
Maybe my expectations were wrong but i would have expect when you pay 20+k€ to a company, to handle a heat system project, that they are taking full accountability. I guess we are learning in the hard way.